Static motor analysers

The new Baker DX series of static motor analysis equipment from SKF replaces older-generation Baker D-series and ST series surge test analysers. The DX is ideal as an entry level instrument for performing motor and generator analysis in areas such as industrial motor test/maintenance, motor servicing and OEM manufacturing.

The SKF Static Motor Analyser, Baker DX offers wide capabilities to analyse all insulation and motor circuits in AC and DC motors, gen¬erators and coils.

The lightweight, portable instruments can carry out low-voltage inductance, impedance, phase angle and capacitance, coil, DC step voltage, winding resistance, Megohm, DC Hipot, surge and DC bar-to-bar armature tests.

They feature an easy-to-use touch screen graphical user interface, are offered with a range of configuration options and accessories and can include the test functions required by the user. Options include coil test, resistance-inductance-capacitance test, DC armature test, simple meg-ohm test and either single- or three-lead configurations.

The low voltage testing capability allows for a more complete testing solution for predictive maintenance or quality management. The low voltage tests can supply up to 600 mA and frequencies from 50 to 4 000 Hz. The Baker DX also offers a modular design that allows for configuration with only the test capabilities needed for the specific application. For example, it can be only a high voltage or a low volt¬age tester or used as a unit that has both high voltage and low voltage testing.

The optional desktop software package - ‘Surveyor DX’ enables data from the tester to be moved to a PC via a USB stick. The software will allow storage of data and report generation.

• Whitelegg Machines Ltd are Britain and Ireland, Sales and Support Agents for Baker Instrument Company, USA (An SKF Group Company)

Tuesday, 3 May 2011

Wind turbine monitoring

Guohua wind turbines choose for SKF remote monitoring

When the fourth biggest wind farm operator in China increases his installed capacity by 50% within one year, that indicates a company that knows its business. And one of the business aspects that all wind farm operators need to take care of is “turbine reliability” – keeping the turbines turning as much as possible and keeping maintenance activities down to a minimum. Reduced or controlled maintenance is always a valuable contribution to bottom line profitability, but when you’ve got 2000 MW of installed capacity, the target by end 2010 for Guohua Energy Investment Company then you are talking about huge amounts of money.

That is why Mr. Zhou Weihua, Deputy General Manager of the Production Department, took a decision in 2008 to evaluate his maintenance strategy and the technology to be applied within that strategy. A critical decision was to look for the most reliable and experienced way to determine the health of his turbines in the fastest and most effective way.


Investigating on-line monitoring
With a few different turbine designs and sizes out in the field he needed the best possible way to get reliable and regular information about the general condition of selected turbines of these designs and types. At the same time he wanted identify any typical negative trends that might occur in the various, but differing, field operating conditions that the turbines would be deployed to. Not being satisfied with his previous assessment process of only using temperature readings of gearbox oil and generator bearing housings, he wanted to investigate on-line monitoring, where vibration signals from critical components are collected 24 hours a day and analysed to determine exactly if and where problems are developing, and how severe any problems were. This type of monitoring would also provide valuable knowledge that could allow critical maintenance to be planned and avoid unexpected and very costly breakdowns. He knew that this type of condition monitoring is widely used in USA, Europe, Australia etc.

Visiting Germany for first hand experience
His first step was to make a deep investigation of what technology was available and the quality and knowledge of the suppliers. These investigations covered all the key suppliers of such technology but contacts with other wind farm operators in China quickly brought him to consider SKF and their turbine monitoring system for further discussions. “Of course I knew of SKF” says Mr Zhou, “they are the number one bearing specialist in the world with expert knowledge in many industries over many years in many countries, also here in China. And I had heard of the SKF WindCon turbine monitoring system but had never used it before.


After direct contact with SKF, I heard that they had recently been successful with remote on-line monitoring, where data from the monitored turbine in the wind farm were transmitted by Internet to their specialists for analysis.


In order to get first hand experience of their remote on-line capability I visited their Intelligence Centre Wind (ICW), their major wind turbine diagnostic centre in Hamburg, Germany”.

At the time of Mr Zhou’s visit the SKF ICW in Hamburg was receiving and processing data from more than 600 turbines from across Europe and also from USA.


“In Hamburg I saw examples of almost all the capabilities of a SKF WinCon system, because there were so many systems deployed in so many wind farms. The level of detail that the system could give was clearly demonstrated, and the explanations by the people making the analysis clearly indicated that they knew all about wind turbines and the critical machinery. The Hamburg visit gave me the confidence to set up a field trial on some turbines in Guohua wind farms in 2009”.

Field trials at 3 wind farms
The field trial involved 11 SKF WindCon systems to be deployed across 3 wind farms; one in Jiangsu province, one in Shadong province and one in Inner Mongolia. Around the time SKF were installing their systems in the Guohua turbines SKF had opened a Remote Condition Monitoring Centre in Shanghai. Having SKF experts so close was an added benefit to Mr. Zhou and he was anxious to get the systems operating and see what the results would be. The data was collected on a local server at each wind farm and transmitted to an SKF server in Shanghai for analysis. Any immediate emergency situation would be reported at once but an ‘emergency situation’ was not detected at start up of the monitoring, and a report was issued once per month to the wind farm site managers and Mr Zhou. The reports contained the detailed vibration spectra for the key components being monitored, together with a brief statement that summarised the analysis of the data in terms of the condition of the component. But there was also a “report grid” that indicated the components being monitored and each one had one of 3 colours; green, yellow or red to give immediate indication of the condition, with green being OK, yellow being a slight to major deviation from the “acceptable levels or trends”, and red being something requiring immediate attention.

The first results were good, because Mr Zhou could “see” for the first time what was really happening with his critical machinery. The SKF WindCon systems delivered the vibration spectra, similar to those he saw in Hamburg, and the SKF experts in Shanghai interpreted the data in terms of the condition of the bearings, potential misalignment, gear damage etc.

During the six months to January 2010, the SKF WindCons provided good information on the turbines allowing Mr. Zhou to determine if and what maintenance would be required. In that period one of the installed SKF WindCons identified a severely damaged generator gearbox bearing at the Inner Mongolia wind farm.

Success and further deployment
“The SKF WindCons did their job,"  said Mr. Zhou, "they kept me informed and the early identification of the severity of the damaged bearing in Inner Mongolia was enough to allow us to plan for replacement at minimum cost and disturbance to the planned electricity supply from the turbine”.

Since the tests Guohua have installed another 58 SKF WindCons and a further 280 have been ordered for new turbines going into service in 2010.

This is the start of a mass application of remote monitoring and Mr. Zhou says “we have some knowledge regarding vibration analysis within our own maintenance teams, but I intend to build up more knowledge within the Guohua organization and set up our own remote monitoring centre in Beijing for our turbines. A lot of this knowledge and assistance will come from SKF as they provide us with their remote diagnostic monitoring during the coming years”.

Thursday, 2 December 2010

Remote wind turbine monitoring in China

Guohua wind turbines choose for SKF remote monitoring

When the fourth biggest wind farm operator in China increases his installed capacity by 50% within one year, that indicates a company that knows its business. And one of the business aspects that all wind farm operators need to take care of is “turbine reliability” – keeping the turbines turning as much as possible and keeping maintenance activities down to a minimum. Reduced or controlled maintenance is always a valuable contribution to bottom line profitability, but when you’ve got 2000 MW of installed capacity, the target by end 2010 for Guohua Energy Investment Company, based in Beijing (CN), then you are talking about huge amounts of money.

That is why Mr. Zhou Weihua, Deputy General Manager of the Production Department, took a decision in 2008 to evaluate his maintenance strategy and the technology to be applied within that strategy. A critical decision was to look for the most reliable and experienced way to determine the health of his turbines in the fastest and most effective way.

Investigating on-line monitoring
With a few different turbine designs and sizes out in the field he needed the best possible way to get reliable and regular information about the general condition of selected turbines of these designs and types. At the same time he wanted identify any typical negative trends that might occur in the various, but differing, field operating conditions that the turbines would be deployed to. Not being satisfied with his previous assessment process of only using temperature readings of gearbox oil and generator bearing housings, he wanted to investigate on-line monitoring, where vibration signals from critical components are collected 24 hours a day and analysed to determine exactly if and where problems are developing, and how severe any problems were. This type of monitoring would also provide valuable knowledge that could allow critical maintenance to be planned and avoid unexpected and very costly breakdowns. He knew that this type of condition monitoring is widely used in USA, Europe, Australia etc.

Visiting Germany for first hand experience

His first step was to make a deep investigation of what technology was available and the quality and knowledge of the suppliers. These investigations covered all the key suppliers of such technology but contacts with other wind farm operators in China quickly brought him to consider SKF and their turbine monitoring system for further discussions. “Of course I knew of SKF” says Mr Zhou, “they are the number one bearing specialist in the world with expert knowledge in many industries over many years in many countries, also here in China. And I had heard of the SKF WindCon turbine monitoring system but had never used it before.

After direct contact with SKF, I heard that they had recently been successful with remote on-line monitoring, where data from the monitored turbine in the wind farm were transmitted by Internet to their specialists for analysis.


In order to get first hand experience of their remote on-line capability I visited their Intelligence Centre Wind (ICW), their major wind turbine diagnostic centre in Hamburg, Germany”.

At the time of Mr Zhou’s visit the SKF ICW in Hamburg was receiving and processing data from more than 600 turbines from across Europe and also from USA.

“In Hamburg I saw examples of almost all the capabilities of a SKF WinCon system, because there were so many systems deployed in so many wind farms. The level of detail that the system could give was clearly demonstrated, and the explanations by the people making the analysis clearly indicated that they knew all about wind turbines and the critical machinery. The Hamburg visit gave me the confidence to set up a field trial on some turbines in Guohua wind farms in 2009”.


Field trials at 3 wind farms
The field trial involved 11 SKF WindCon systems to be deployed across 3 wind farms; one in Jiangsu province, one in Shadong province and one in Inner Mongolia. Around the time SKF were installing their systems in the Guohua turbines SKF had opened a Remote Condition Monitoring Centre in Shanghai. Having SKF experts so close was an added benefit to Mr. Zhou and he was anxious to get the systems operating and see what the results would be. The data was collected on a local server at each wind farm and transmitted to an SKF server in Shanghai for analysis. Any immediate emergency situation would be reported at once but an ‘emergency situation’ was not detected at start up of the monitoring, and a report was issued once per month to the wind farm site managers and Mr Zhou. The reports contained the detailed vibration spectra for the key components being monitored, together with a brief statement that summarised the analysis of the data in terms of the condition of the component. But there was also a “report grid” that indicated the components being monitored and each one had one of 3 colours; green, yellow or red to give immediate indication of the condition, with green being OK, yellow being a slight to major deviation from the “acceptable levels or trends”, and red being something requiring immediate attention.

The first results were good, because Mr Zhou could “see” for the first time what was really happening with his critical machinery. The SKF WindCon systems delivered the vibration spectra, similar to those he saw in Hamburg, and the SKF experts in Shanghai interpreted the data in terms of the condition of the bearings, potential misalignment, gear damage etc.

During the six months to January 2010, the SKF WindCons provided good information on the turbines allowing Mr. Zhou to determine if and what maintenance would be required. In that period one of the installed SKF WindCons identified a severely damaged generator gearbox bearing at the Inner Mongolia wind farm.

Success and further deployment of SKF WindCon

“The SKF WindCons did their job," said Mr. Zhou, "they kept me informed and the early identification of the severity of the damaged bearing in Inner Mongolia was enough to allow us to plan for replacement at minimum cost and disturbance to the planned electricity supply from the turbine”.

Since the tests Guohua have installed another 58 SKF WindCons and a further 280 have been ordered for new turbines going into service in 2010.

This is the start of a mass application of remote monitoring and Mr. Zhou says “we have some knowledge regarding vibration analysis within our own maintenance teams, but I intend to build up more knowledge within the Guohua organization and set up our own remote monitoring centre in Beijing for our turbines. A lot of this knowledge and assistance will come from SKF as they provide us with their remote diagnostic monitoring during the coming years”.

Monday, 4 January 2010

PdM in China

Predictive Maintenance (PdM) benefits overall maintenance strategy at gas plants in China

The Linde Group is a world leading gases and engineering company operating in more than 100 countries. With such large and widespread successful operations it is no surprise that maintenance activities are well run and that the company is no stranger to advanced monitoring techniques and equipment. In USA and UK particularly, but also elsewhere in the world, on-line machine monitoring has been used for a number of years at Linde plants. And, at its Shanghai headquarters it has a large and impressive ‘remote operations centre’ where it monitors and tracks the process operations of all it’s major gas plants in China 24 hours a day !

But Henry Aung-Kyi, Linde Reliability Engineering Manager for Greater China also knows that the key to successful maintenance operations is the right balance of techniques, systems and methodologies. An experienced and knowledgeable engineer, he is convinced of the value of highly sophisticated on-line monitoring system – for critical machinery- but, for some of the plant equipment at his gas plants, this level of technology and cost is not needed for optimum management of his company’s resources. And he has, for a long time, believed in the value of predictive maintenance (PdM), even if there is a price to pay in terms of time to acquire the skills and train the workforce.

Many process and manufacturing plants operate preventive maintenance activities (PM). PM activities are usually time based, with machine adjustments and replacements parts being made on a routine basis without regard of the operational performance or condition of the major piece of equipment or its component parts. However, predictive maintenance (PdM) is a ‘condition’ based approach that builds a picture of the anticipated condition of a component or piece of equipment based on trend data taken while the equipment is in service. Such data is mostly vibration analysis data, but can include lubricant analysis, temperature measurements etc. Based on this trend data, and applying principles of statistical process control, an engineer can predict when is the best time to carry out maintenance activity. This allows him to plan work when it is most cost effective with a full understanding of the relative performance loss at risk. Since most PdM actions are made while equipment is in service there is minimal disruption to production and can result in substantial cost savings and higher equipment reliability.

Integrating into Linde’s High Performance Organisation
When Linde Group acquired the BOC gases company in 2006 it embarked on a programme of integration of it’s new assets in China into Linde’s “High Performance Organisation”. With Linde operations and maintenance being process driven, focusing on process optimisation and continuous improvement it was only natural for Aung-Kyi to assess the situation at each plant separately and develop a plan for improvement to the next level of technology. The long term goal is to bring all maintenance activities at all plants to the same advanced level, and share information and knowledge for optimal benefit. But, that will take time due to differences in the existing experience at each plant and the required level of learning needed by the workforce at each plant.

So the Nanjing plant (joint venture with Sinopec SPC) was the first plant selected for a pilot application of a predicitive maintenance programme (PdM). Before running the pilot application Linde invited specialist companies, including local Chinese suppliers, to do some PdM service work at the Nanjing plant and propose a long term programme along with details of the services provided and the costs and anticipated benefits to Linde. After one year of trials and discussions with the competing vendors Linde selected SKF to start up the PdM activity for their operations in China. When asked about the reasons for their choice Aung-Kyi said “a number of key points separated SKF from the other vendors. As well as providing excellent services in the actual monitoring of the plant they showed their experience by identifying what equipment to monitor and went on to produce work recommendations that were far broader than the other vendors. Naturally, the local Chinese vendors had a price advantage, even though the SKF people are from the local SKF China organization, but from SKF we got more than just a ‘condition report’. We got constructive feedback of a depth that local suppliers could not match and a feeling that they really knew the machinery under investigation and had as much desire as Linde to manage that equipment efficiently. And that transmitted a huge amount of confidence to the local Linde engineers, which is really needed to get PdM understood and implemented properly. It wasn’t enough that I was satisfied with a particular vendor. What was really important was that the plant engineers in Nanjing wanted the vendor, and effectively it was joint decision by myself and the actual Linde people receiving the service, to select SKF. In addition I knew we were embarking on a period of growth and that we would need an experienced and stable supplier that could support us as we grew, so I was very happy to select SKF who are also a global vendor with a large and also growing presence in China ”


Consolidating and widening PdM in the China region
There are now 9 Linde plants in China running PdM programmes. The SKF engineers make a 3 monthly visit to the plants to take measurements and follow up with in-depth discussions and recommendations as necessary. All data is uploaded to a central Linde database where all plants can access, and benefit from, the historical trending data for the particular equipment being monitored, many of which are applied in more than one plant. Simon Chen is Linde’s condition based monitoring specialist for Greater China and he has many years experience in condition monitoring applications on many kinds of rotational machinery eg; compressors, motors, gearboxes, fans, pumps, etc. He oversees the internal coordination of knowledge transfer between the 9 Linde plants to ensure the company extracts the maximum benefits in the shortest time. During the process of delivering the service to these 9 plants, Chen’s experience has assisted greatly to enable SKF reliability engineers to make effective condition based maintenance monitoring to Linde and this is enhancing the overall quality of SKF service.

The main equipment being monitored are the high speed compressors and ancillary equipment such as pumps and expansion machines. Readings are taken at positions on the compressor that indicate the ‘condition’ of each of the compressor stages, and this is important to the overall efficiency of the compressor. Using SKF’s portable data collector Microlog CMVA60 or CMXA70, measurements are routinely and easily collected without any disturbance to operations. Relevant data is also compared with that collected by the integrated distributed control system (DCS) in the compressor. The DCS data is needed to control and protect the production process and it measures flows, pressures, shaft vibrations etc, so that very fast automatic decisions can be made depending on what is measured. Any strong deviations between the SKF data and the DCS data are then discussed to the point of deciding what corrective action is to be taken.

Success and a growing cooperation
Commenting on the situation now Aung-Kyi said “at the time that the pilot application was started Linde had a lot of projects running, so the success of the pilot was very much in the ‘own hands’ of the vendor company. They had to really work hard to inform, educate and train the local Linde engineers how to handle and assess their machine data in order to get the most understanding how to go further. The standards set by SKF were very high, also with respect to understanding the necessary safety standards, which was, and still is, a growing priority throughout Chinese process and manufacturing industries. Today the confidence in PdM routines and associated technology is beyond question in Linde. We have seen a gradual understanding that PdM is a very vital part of a maintenance strategy, especially because processes like our gas production are particularly suited to PdM. Machines and equipment normally run well for a very long time. Problems come later when the first signs of deteriorating performance are caused by wear, unbalance, misalignment, overheating etc. By detecting these conditions early enough we can monitor and run the machinery at optimal acceptable performance without risking catastrophic breakdown that would disrupt production and have huge downtime and cost consequences. We also got to benefit from the SKF global experience of doing maintenance assessments on many process plants including those that use many of the different makes of compressors, motors, pumps, gearboxes etc used in our plants. Their global asset performance and maintenance database is accessible to their China colleagues and is a ‘living’ repository of valuable information, being added to every day, that is almost impossible to acquire by client companies such as ours. We can look at SKF best practices for machinery operation and use that as a guide to what to expect from our existing and new machinery as we expand our business. We see SKF as a valuable strategic partner in China and have come to rely on first class engineering support from them, which we always get !!"